Who Is Already Winning Work Behind Google's $17 Billion Campus? ATI follows Google's Project Tembo to a new CSE Global equipment award, Bechtel's power-hub role and supplier entry points in Cheyenne, Wyoming.
2026-09-25
A September 24 equipment award shows the supply chain behind Google's proposed Wyoming campus is already taking shape. Here are the companies and entry points worth investigating.
Tallgrass and Mitsubishi Power signing, May 2026. Photo: Mitsubishi Power
I started with Google's proposed $17 billion Project Tembo in Laramie County, Wyoming. I wanted to know where a business could actually enter the supply chain.
Following the power infrastructure led to an announcement in Singapore, published yesterday.
On September 24, CSE Global disclosed a follow-on order to design and manufacture power distribution centers for the Cheyenne Power Hub. The company expects to execute that contract during 2026 and 2027. CSE Global release
Google's own project website puts the campus's peak construction workforce in late 2029 through mid-2030. Project Tembo FAQ
Those are different scopes and different milestones. Together, they make a useful point for a supplier watching this market: important purchasing decisions can happen years before the campus reaches its busiest construction period.
The equipment order behind the announcement
Exact excerpt from the CSE original release. The US$150M figure covers two projects; Cheyenne was not split out.
CSE's disclosure names the Cheyenne Power Hub and says its equipment will distribute electricity to the adjacent data center. It gives us a supplier, a defined product and an execution window.
The word worth noticing is "follow-on". Reporting on the release records that the Cheyenne order was initially announced on August 14, 2026, which makes September 24 a second award on the same scope rather than a first. Repeat orders are a better signal of sustained procurement than a single announcement. Business Times
There is a number worth handling carefully. CSE announced US$150 million of contracts in total, covering both Cheyenne and an unrelated Louisiana LNG project at Calcasieu Pass 2. It did not break out the value of the Cheyenne follow-on order. The full US$150 million cannot be assigned to Wyoming.
The order is already awarded. Its significance for other businesses is that it reveals part of the delivery chain: who has work, what that work involves and when execution is expected.
For a manufacturer or distributor, that is the starting point for investigating complementary equipment, material and service requirements. It does not establish that CSE is currently seeking additional suppliers.
Then I found the power-hub EPC
Kimley-Horn site plan dated November 21, 2025. Historical planning document, not current as-built conditions.
I checked Bechtel's own project descriptions. A current electrical-superintendent listing states that its Renewables and Clean Power team "have signed the EPC contract for the Cheyenne Power Hub Project". It describes work involving transformers, cable installation and energization. Bechtel listing
The useful finding is Bechtel's stated project role. I am not treating a recruitment advertisement as proof of a labor shortage or an open subcontract.
Bechtel also maintains a public supplier-registration route. That gives an industrial supplier or specialty contractor a specific organization to qualify with and a project to ask about. Bechtel supplier hub
I checked its public project-opportunity report too. The version linked on its website was dated August 17 and did not list Cheyenne. That limits the claim: a supplier entry point is verified; a currently open Cheyenne package is not. Project opportunities
The power infrastructure has other named participants. Tallgrass and Mitsubishi Power announced two turbines for the first phase in May, with approximately 1,150 MW of expected capacity. That equipment announcement is another reason to follow the energy project on its own timetable. Mitsubishi Power
Google's campus is a separate project to track
Laramie County's July 8 memo explains how the campus changed. Crusoe withdrew from the earlier Project Jade proposal. Google, doing business as Jupiter Star Holdings, entered the revised application process. The updated plan reduced five buildings to four and the projected construction peak from 5,000 workers to 2,500. County memo
The same memo said construction phases on Tallgrass's associated power hub were already underway.
That history matters commercially. An account list built from the first announcement could carry an outdated developer and workforce assumption. It could also collapse the campus and its supporting infrastructure into one supposed buyer.
Google's current FAQ points interested local businesses to its contact form and says union and non-union trade partners can compete. The campus targets pre-construction around Q4 2026, with peak staffing projected for Q4 2029 to Q2 2030.
Bechtel's verified role concerns the power hub. The records reviewed for this investigation do not establish that Bechtel is the general contractor for Google's data halls.
ATI led me to another buyer in the same market
A separate campus with a separate delivery team. Photo: Clayco
Next I checked American Trades Index's Laramie County project records. One named development was Related Digital's Cheyenne campus.
I followed that record to the developer's announcement and Clayco's project page. Both identify Clayco as construction manager for the initial phase. CoreWeave is the anchor tenant for the first 88 MW of critical IT capacity. Related Digital , Clayco project page
This is a separate campus with a separate delivery team. Related's October 2025 announcement targeted initial completion in late 2026; that historical target is not confirmation of completion today.
Clayco publishes a prequalification process and a public plan-room route. The plan room requires a BuildingConnected profile, and project-specific bid availability still needs checking. Clayco prequalification
That is how the ATI market view becomes useful: the initial Google lead turns into a regional account list grounded in identifiable projects and delivery organizations. Whether those projects compete for the same crews or equipment requires package schedules, not simply adding their announced budgets together.
A note on what the license register can and cannot tell you here
ATI holds 62 current electrical license records placed in Laramie County. That figure should not be read as the county's electrician population, and this piece does not use it as one.
Wyoming's register also publishes no status field at all. A record counted as current here is inferred from a future expiry date rather than a published active status, which is a weaker claim than a plain count suggests and is not comparable with a state that publishes status directly.
County placement is weak here too: only about 3.6% of Wyoming's electrical records carry a county we can resolve, and of the Laramie-placed electrical records, effectively all are contractor or business credentials rather than individual journeyman or master licenses. Wyoming also issues no state-level plumbing license at all, so an absent trade line is a licensing fact, not a shortage.
I am stating this because the interesting question here is procurement, not supply. Anyone modeling crew availability for this market needs a better instrument than a county license count, and we would rather say so than publish a ratio that looks precise and is not.
The question becomes: which obligation, which buyer, which date?
For a sales team, separating the projects helps identify where to direct a qualification effort. For an owner or EPC planning delivery, it makes the equipment, power and campus milestones easier to investigate individually.
The same distinction matters when evaluating project risk. A supplier's 2026 to 2027 execution window and a campus's later staffing peak do not establish when equipment ships, who carries it in transit, when custody changes or what happens if an interface slips. Those answers belong in the relevant contracts and schedules.
We have not verified the equipment purchaser's identity, the complete subcontract chain, project insurance placements or financing mandates. Those remain diligence questions, not opportunities we can advertise as available.
Where to take the next conversation
Registration is an entry point, not an invitation to bid.
If your company supplies industrial electrical products or services, start with Bechtel's supplier hub . Register or update your capabilities, identify Cheyenne Power Hub as the project of interest, and ask who manages the relevant purchasing category.
For the Google campus, use the Project Tembo contact form . For the separate Related Digital development, review Clayco's prequalification process .
Bring a precise question: what remains unawarded in our scope, who controls that purchase, and when must it arrive?
The September 24 order makes this more than a future-investment story. Part of the supply chain is already taking shape. If you want to participate, learn the buying relationships while there is still time to qualify for the work that remains.
Related in the Index The American Trades Index